• Skip to primary navigation
  • Skip to main content
  • Skip to footer
  • Events
  • Join Our Team
  • Media Resources
  • In the News
  • Blog
Donate Patient Portal
Family First Health

Family First Health

A community health care center

  • Schedule Appointment
  • Services
    • Medical Services
      • Integrated Substance Use Services
      • Integrated Behavioral Health Services
      • Optometry
    • Dental Services
      • Mobile School Dentist Program
    • Community Health Programs
      • Caring Together
      • Nurse-Family Partnership
      • Connections For a Healthy Pregnancy
    • COVID-19 Information
  • Providers
  • Patient Info
    • Patient Info & Forms
    • Insurance & Sliding Fee
    • Patient Portal
  • Locations
    • Columbia Dental
    • Columbia Medical
    • George Street
    • Gettysburg
    • Hannah Penn
    • Hanover
    • Lebanon
    • Lewisberry
  • Watch
    • Vaccine Stories
    • Community Health Briefings
    • Let’s Talk Health
  • About
    • Careers
    • Contact
    • Financials

Construction at GSC – 2022

You are here: Home / Construction at GSC – 2022

Please note that the timeline is subject to change. We’ll update impacted staff of any major changes.
If you have specific questions, please contact your supervisor.

If you are in need of boxes or totes to move things from your desks, please contact Chris George.

Want to see photos of the construction? Visit our gallery: GSC Construction 2022

June 6 – early August

Phase 1A:
2nd floor – Chart Room & QI area

Demo on 2nd floor – chart room, QI office area
Includes building of temporary plastic walls outside of chart room and QI area, removal of drop ceiling and flooring, mechanical, electrical, and plumbing demo
Approximately 1 week (June 6 through June 14)


Metal stud framing and drywall – building new walls in the chart room area, MR area, QI office, Mery’s office.
Approximately 18 days (June 13 through July 6)


Installing doorframes
Approximately 3 days (July 7 through July 11)


1st coat Painting in chart room, QI office area, etc.; duct work and electrical work
Approximately 4 days (July 5 through July 8)


Acoustical Ceiling Grid in ch
art room and QI office area, Install Ceiling Lights and HVAC diffusers
Approximately 5 days (July 8 through July 13)

Fire protection work (sprinklers, etc.)
Approximately 3 days (July 13 through July 15)


Paint final coat in chart room, QI area, new offices in MR area. Build partition walls in workspaces.
Approximately 3 days (July 18 through 20)


Painting in rest of Medical area – lobby walls, back through pods, etc.

Flooring installation – Following behind the painters. Will begin in – beginning in the evening of July 27

Reassemble desk/cubicles in offices and MR/SUS/CHW workspaces

Moving back into the chart room area

HVAC zones

Office doors


Still to be completed –>
Security Door at check out

July 21 – August 18

Phase 1B:
2nd Floor behind Pods – NIGHT WORK
Dental Department work (more info soon!)

Demo in the area behind the pods on the 2nd floor – restrooms, storage areas, etc. This will begin with removing partitions in the restrooms during the daytime hours on July 21-22. Restrooms will be unavailable beginning July 21. Including mechanical, electrical, and plumbing.

Metal framing and insulation

Mechanical, Electrical, Plumbing work

Install doorframes

Painting in Medical and Dental areas

Re-install ceiling tiles

Fire protection work (sprinklers, etc.)

Mechanical, Electrical, Plumbing trim work

Final painting in medical

Flooring installation in 2nd floor lobby and dental

New furniture assembly and delivery

HVAC zones

Office doors


Still to be completed:
Moving supply closet items back into place
Final inspection

August 15 – end of October

Phase 2:
3rd Floor – Admin/IT area (daytime hours)

Demo – restrooms on admin side, IT area
Approximately 5 days (August 15 through 19)

Metal stud framing, insulation, drywall
Approximately 11 days (August 22 through September 5)

Mechanical, Electrical, Plumbing rough in
Approximately 3 days (September 6 through September 8)

Install doorframes
Approximately 3 days (September 6 through September 8)

Painting
Approximately 4 days (September 7 through September 12)

Re-install ceiling tiles
Approximately 3 days (September 8 through September 12)

Fire protection work (sprinklers, etc.)
Approximately 3 days (September 13 through September 15)

Mechanical, Electrical, Plumbing trim work
Approximately 5 days (September 13 through September 19)


Still to be completed:
Flooring installation (happening now!)
Moving back into the IS area and new 3rd floor offices

September and October

Exterior Work

Power washing exterior of building
Making casts of damaged areas for repair
Painting
Dealing with road construction at the same time

May 16 – June 3

COMPLETED: Pre-Construction:
2nd floor – Chart Room & QI area

Move team out of chart room – MRs, CHWs, SUS – by Friday, May 27
Move team out of QI area – by Friday, May 27

Disassemble all cubicles/desks in this area (these will be moved to the 1st floor Windows Room area for storage) – by Friday, June 3

Join Our Family

Sign up for occasional emails tailored towards family and community well-being.

Sign Up

From Our Patients

  • The receptionists are very pleasant. I would recommend this office to any of my friends who might need a doctor or dentist. The fact that they have someone who can help translate for my family has been such a convenience. I can't thank them enough.
    Gettysburg Site Patient
    Mrs. H | Gettysburg, PA
  • I've had some of the best experiences when using their dental services as well as the plethora of other services they provide. I really like the staff and they have all been super nice and friendly, I recommend that people take advantage of the services they provide!
    George Street Site Patient
    Dirk | York, PA
  • I love this place. My kids are addressed by their names, fast to get us in to be seen, its clean, very friendly. Always have a warm atmosphere. I LOVE IT HERE, first time I trust a practice with my babies!
    Columbia Site Patient
    Milagros | Columbia, PA
  • This is the most friendly, caring, and compassionate doctors office I've ever been to. You are a person with concerns and issues and ailments to them and they do everything they can to help. Everything is explained so you completely understand what the next step is.
    Lewisberry Site Patient
    Heather | Lewisberry, PA

Footer

Contact

Contact Us

717-845-8617

Patient Portal

  • YouTube
  • Facebook
  • Twitter
  • LinkedIn
  • Instagram

About

  • About Us
  • Locations
  • Our Providers
  • News

Patients

  • Medical Services
  • Dental Services
  • Services
  • Patient Portal
  • Insurance & Sliding Fee

Careers

  • Careers
  • Job Listings
  • Staff Login

All Content © 2023 Family First Health
Legal Disclaimer • Privacy Policy